Case studies

An Accumine model was developed for operating and capital cost estimates for the life of mine options. The mine production and equipment schedules were undertaken within a mine planning system and interfaced into Accumine using standardised CSV files. These inputs along with other modelling inputs were used to develop a detailed, first principles build up of operating costs and equipment capital. This information was interfaced into a corporate valuation model and analysis was undertaken in PowerBI.

The Accumine solution allowed ten different operating scenarios to be run on a single model, meaning only one framework had to be maintained and updated allowing more time for analysis.

Framework icon

Generating a new operating scenario was simply a click of a button – to copy an existing scenario and importing revised physical and equipment schedules.

Repeat icon

Accumine was integrated to a PowerBI analysis package that allowed the modeller to validate inputs/outputs and understand key drivers between scenarios.

auditable icon

Having both Accumine and PowerBI web based allowed data to be easily shared with multiple people. Additionally, a standardised CSV output could be fed into the client’s corporate valuation model.

Similar Accumine modelling frameworks and process have been used on studies relating to processing plant upgrades and its effect on the mine plan and different mining studies assessing impacts of type and location of infrastructure, creeks, and alike.

auditable icon

Accumine allowed models to be accessible by simply adding a user, rather than using FTP sites to share information.

A standardised CSV output was configured to feed into the client’s corporate valuation model.

fast icon

The use of a common framework accommodating multiple scenarios meant the process to generate a revised scenario based on changed inputs and assumption was fast.

Quick model building allowed more time to analyse and understand key inputs and outputs.

analyse icon

Multiple lists were used in the development of the model, so key activities, equipment, and cost types could easily be quantified. The Pivot View functionality allowed for the data to be ‘sliced and diced’ to better understand the outcome.

Factored physicals were calculated as part of the Accumine cost model. The Accumine model imported the base assumptions such as consumption rates by development profile (e.g. 0.9m, 1.8m, 2.4m, and 3.0m split sets per metre) and the mine plan (e.g. metres of development by profile).

Templates were developed for each key area of derived physicals such as drill metres, ground support consumables, and drill and blast consumables. The templates were then associated with each development profile generating the hundreds of factored physicals and consumables. The resulting schedule of consumables could then be costed based on unit rates.

fast icon

The inclusion of the derived physicals in the Accumine cost model meant that scenarios and iterations could be reliably run with a short turn around when new mine plan cases were generated.

Template icon

The use of templates meant that the large number of factored physicals items could be generated quickly and reliably. For example, the “Key Consumables” template was applied to the fifteen development profiles and ten ground support profiles following the creation of the 45 elements of the template rather than 45 elements created for each of the 150 possible unique combinations.

analyse icon

Different views of the mine planners and the cost modellers to validate the inputs and assumptions and workings of the model.

Book a demo

Name(Required)
This field is for validation purposes and should be left unchanged.